TGI FRIDAYS

 

With a construction schedule of an estimated 10 weeks from start to finish, this full interior and exterior renovation was completed with the newest concept standards.

 

SERVICES: Redevelopment, Renovation, Interior Build-Out, and Construction Management

 

LOCATION: Mansfield, Ohio

 

YEAR COMPLETED: 2015

 

BUILDING SIZE: 6,800 Square Feet

 

Requirements:

  • The building was originally constructed in 1996 as a TGI Fridays, was later converted to Johnny Big’s, and the ownership requested the space be re-converted back to TGI Fridays.

  • The requirement was to close the current restaurant, fully remodel the interior and exterior, update with all new kitchen and bar equipment, and complete the renovation by Valentine’s Day in 2016.

Objectives / Challenges:

  • The construction schedule was an estimated 10 weeks from start to finish.

  • The most challenging aspect was part of the design team’s location stationed out of state and having to coordinate between entities throughout the country that were all intermingled in this project.

Results:

  • In 10 weeks, Premier renovated with the newest concept standards which included a more steamlined, patron friendly design, and a warmer color scheme to create an inviting atmosphere.

Download Case STUDY

BACK TO RETAIL / HOSPITALITY

PREMIER DEVELOPMENT PARTNERS © 2015